Mission Rock

Mission Rock

Results

  • On-time project delivery supported by early utility planning and strategic coordination
  • Reduced trench length and streamlined construction through composite joint trench strategy
  • City plan checks accelerated due to accurate, complete utility design packages
  • Navigated multi-agency complexity, including SFPUC, PG&E, AT&T, Comcast, and DT
  • Delivered approved public street lighting system, fully integrated into utility plan set

Solution

PSD led the utility design and coordination efforts for this landmark San Francisco neighborhood:

  • Developed the MEIP and Master dry utility layout and agency coordination
  • Joint trench composite plan incorporating power, gas, telecom, fiber, CATV, and street lighting
  • PG&E Rule 15/16 gas planning (WRO removal & relocation)
  • PG&E Overhead Removal/Relocation (WRO)
  • SFPUC electric utility planning and WDT coordination
  • Telecom design and layout for AT&T, Comcast, and City of SF Department of Technology (DT)
  • Full public street lighting system design, including photometric modeling and comment resolution
  • Close collaboration with the development team and civil engineers from preconstruction onward
  • Coordination of utility easements, trench sequencing, and long-term constructability
  • PSD’s deep experience and longstanding relationships with City utilities — particularly SFPUC — enabled the team to resolve friction points and move the design forward faster than typical for projects of this scale.

Challenge

Mission Rock’s location and complexity posed major infrastructure hurdles:

  • Jurisdictional overlap between SFPUC, PG&E, Port of SF, and City departments
  • Conflicting utility standards across agencies and inconsistent review feedback
  • A relatively new electric utility provider (SFPUC) with evolving construction/design standards
  • Sequencing pressure to clear PG&E overhead and gas facilities ahead of early horizontal improvements
  • Political and jurisdiction friction between SFPUC and PG&E required strategic coordination
  • PSD became the glue that held the multi-agency utility effort together.

Impact

Thanks to PSD’s detailed planning and coordination:

  • Utilities were delivered on time and to spec, avoiding costly rework
  • Utility trenching was optimized and reduced, lowering capital cost
  • Plan check cycles were shortened due to clear, coordinated design sets
  • RFI count was minimized during construction
  • Client maintained momentum to deliver housing, retail, and infrastructure per schedule

Let’s Work Together Dry utility design that helps your
project move forward.